Question: Given the following network and activity time estimates, determine: 1. The expected time and variance for each activity 2. The critical path. This must be

Given the following network and activity timeGiven the following network and activity time estimates, determine:

1. The expected time and variance for each activity

2. The critical path. This must be based on your calculations of the start and finish times and not by inspection.

3. Complete the chart showing both LF and EF figures.

D 6,8,19 E A 3,11,14 5,9,14 - F 2,19,38 2.9.14 G Start 1,6,15 2,5.8 Finish K H 1,8,13 4,8,15 3,7,10 J NB: 3.11.15 1. Time periods are in weeks 2. Round off times to two decimal places where fractional. 3. You may work in the network but please show the results in a table

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!