Question: Given the following network and activity time estimates, determine: 1. The expected time and variance for each activity 2. The critical path. This must be
Given the following network and activity time estimates, determine:
1. The expected time and variance for each activity
2. The critical path. This must be based on your calculations of the start and finish times and not by inspection.
3. Complete the chart showing both LF and EF figures.
D 6,8,19 E A 3,11,14 5,9,14 - F 2,19,38 2.9.14 G Start 1,6,15 2,5.8 Finish K H 1,8,13 4,8,15 3,7,10 J NB: 3.11.15 1. Time periods are in weeks 2. Round off times to two decimal places where fractional. 3. You may work in the network but please show the results in a tableStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts