Question: Given the following Project Activity Description and Network Diagram, select the Critical Path. table [ [ Activity , Duration,Predecessor,ES , EF , LS ,

Given the following Project Activity Description and Network Diagram, select the Critical Path.
\table[[Activity,Duration,Predecessor,ES,EF,LS,LF,SLACK],[A,4,-,0,4,0,4,0],[B,12,A,4,16,9,21,5],[C,17,A,4,21,4,21,0],[D,5,A, B, C,21,26,21,26,0],[E,11,B, D,26,37,26,37,0],[F,9,C, D,26,35,28,37,2],[G,3,E, F, G,37,40,37,40,0]]
 Given the following Project Activity Description and Network Diagram, select the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!