Question: Given the following Project Activity Description and Network Diagram, select the Critical Path. table [ [ Activity , Duration,Predecessor,ES , EF , LS ,

Given the following Project Activity Description and Network Diagram, select the Critical Path.
\table[[Activity,Duration,Predecessor,ES,EF,LS,LF,SLACK],[A,5,-,0,5,0,5,0],[B,17,A,5,22,5,22,0],[C,14,A,5,19,8,22,3],[D,10,A, B, C,22,32,22,32,0],[E,11,B, D,32,43,33,44,1],[F,12,C, D,32,44,32,44,0],[G,1,E, F, G,44,45,44,45,0]]
 Given the following Project Activity Description and Network Diagram, select the