Question: Given the following table, construct an AOA network and answer the following three questions. Note: You need to completely comply with the six rules of

Given the following table, construct an AOA network and answer the following three questions. Note: You need to completely comply with the six rules of AOA while setting up AOA.

Activity Duration (days) Immediate Predecessors
A 6 NONE
B 9 NONE
C 8 A,B
D 7 A,B
E 10 D
F 12 C,E

(1) There should be how many paths? (2) Critical length is how many days? (3) There should be how many non-critical activities? (4) There should be how many dummy arc(s) in the AOA network?