Question: Given the following table, construct an AOA network and answer the following three questions. Note: You need to completely comply with the six rules of
Given the following table, construct an AOA network and answer the following three questions. Note: You need to completely comply with the six rules of AOA while setting up AOA.
| Activity | Duration (days) | Immediate Predecessors |
| A | 6 | NONE |
| B | 9 | NONE |
| C | 8 | A,B |
| D | 7 | A,B |
| E | 10 | D |
| F | 12 | C,E |
(1) There should be how many paths? (2) Critical length is how many days? (3) There should be how many non-critical activities? (4) There should be how many dummy arc(s) in the AOA network?