Question: Draw the AOA path first (1) There should be dummy arc(s). (2) The critical length is days. Given the following table, construct an AOA network

Draw the AOA path first
(1) There should be dummy arc(s).
(2) The critical length is days.
Given the following table, construct an AOA network and answer the following four questions. Note: You need to completely comply with the six rules of AOA while setting up AOA. Activity Immediate Predecessor(s) Time Duration (days) A E 2 00 AD 3 B 4 D E 5 E None 10 TI E 14Step by Step Solution