Question: Draw the AOA path first (1) There should be paths. (2) There should be dummy arc(s). (3) The critical length is days. (4) There should

Draw the AOA path first (1) There should be

Draw the AOA path first

(1) There should be paths.

(2) There should be dummy arc(s).

(3) The critical length is days.

(4) There should be non-critical activities.

Given the following table, construct an AOA network and answer the following four questions. Note: You need to completely comply with the six rules of AOA while setting up AOA. Activity Immediate Predecessor(s) Time Duration (days) A E 24 B G 3 F G 12 D F G 11 E 12 F None 8 G None 7 H B, C, D 5 5