Question: Given the following task time estimates (HOURS), Task a m b Predecessor A 31 40 60 B 15 20 25 C 17 25 41 A
Given the following task time estimates (HOURS),
| Task | a | m | b | Predecessor |
| A | 31 | 40 | 60 | |
| B | 15 | 20 | 25 | |
| C | 17 | 25 | 41 | A |
| D | 15 | 19 | 26 | A, B |
| E | 20 | 25 | 30 | C, D |
| F | 18 | 24 | 31 | E |
| G | 11 | 18 | 22 | F |
a. How long is the project length (round to two decimal places)? [ Select ] ["127.45", "135.78", "134.83", "128.00", "122.89"] .
b. What tasks form the critical path? [ Select ] ["B, D, E, F, G", "A, C, E, F, G", "A, D, E, F, G", "B, C, D, E, F, G", "A, B, C, E, F, G"] , and what is the project variance and standard deviation (round to two decimal places) [ Select ] ["56.33 and 7.51", "50.19 and 7.08", "34.56 and 4.78", "44.35 and 5.34", "58.01 and 8.22"] .
c. How much slack is there in activity C? [ Select ] ["12 hours", "29 hours", "6 hours", "8.34 hours", "0"] How much slack in activity D? [ Select ] ["28.66 hours", "12.78 housr", "6.83 hours", "0, it is on the critical path", "4.56 hours"]
d. What is the probability that the project will be completed in 137 hours? [ Select ] ["62%", "27%", "38%", "47%", "75%"]
e. How many hours would be required to be 85% sure of completion? [ Select ] ["142", "15 additional hours", "157", "same as the original project length", "a reduction of 15 hours"]