Question: Given the following task time estimates ( HOURS ) , TaskTimePredecessorA 4 0 B 2 0 C 2 5 AD 1 9 A , BE

Given the following task time estimates (HOURS),TaskTimePredecessorA40B20C25AD19A, BE25C, DF24EG18Fa. How long is the project length? .b. What tasks form the critical path? c. What is the LS/LF for activity D.?.d. How much slack is there in activity C? How much slack in activity D? e. What if activity D. was delayed by 7 hours, what would be the project length and critical path? f. Referring to letter e., how much slack would be in activity B.?