Question: Given the following task time estimates ( HOURS ) , TaskTimePredecessorA 4 0 B 2 0 C 2 5 AD 1 9 A , BE
Given the following task time estimates HOURSTaskTimePredecessorABCADA BEC DFEGFa How long is the project length? b What tasks form the critical path? c What is the LSLF for activity Dd How much slack is there in activity C How much slack in activity D e What if activity D was delayed by hours, what would be the project length and critical path? f Referring to letter e how much slack would be in activity B
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
