Question: Given the project within the table below, calculate the following: Activity Predecessor Time (days) A 2.5 B 3.7 C 7.5 D A, C 8.8 E

Given the project within the table below,

Given the project within the table below, calculate the following: Activity Predecessor Time (days) A 2.5 B 3.7 C 7.5 D A, C 8.8 E D 10 IF B, E 4.2 G F 9.7 H G 11.5 a. What is the project length? [Select] b. What activities are on the critical path? [Select] c. How much slack is in activity A? [Select] and activity G? [Select] d. What is the Late Start / Late Finish for activity E? [Select] e. What would happen to the overall project length if activity A was delayed by 6 days, now taking a total of 8.5 days? [Select]