Question: Given the project within the table below, calculate the following: Activity Predecessor Time ( days ) A - - 7 . 5 B - -

Given the project within the table below, calculate the following:
Activity Predecessor Time (days)
A --7.5
B --9.7
C --10.5
D A, C 8.8
E D 10
F B, E 4.2
G F 9.7
H G 11.5
a. What is the project length?
[ Select ]
b. What activities are on the critical path?
[ Select ]
c. How much slack is in activity A?
[ Select ]
, and activity B?
[ Select ]
d. What is the Late Start / Late Finish for activity B?
[ Select ]
e. What would happen to the overall project length if activity E was delayed by 4 days, now taking a total of 14 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!