Question: Given the project within the table below, calculate the following: Activity Predecessor Time ( days ) A - - 7 . 5 B - -
Given the project within the table below, calculate the following:
Activity Predecessor Time days
A
B
C
D A C
E D
F B E
G F
H G
a What is the project length?
Select
b What activities are on the critical path?
Select
c How much slack is in activity A
Select
and activity B
Select
d What is the Late Start Late Finish for activity B
Select
e What would happen to the overall project length if activity E was delayed by days, now taking a total of days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
