Question: Given this information about an activity: ES = 19, EF = 27, LS = 26 and LF = 34, determine the following Determine if there
Given this information about an activity: ES = 19, EF = 27, LS = 26 and LF = 34, determine the following
Determine if there is slack in this work activity, and if so, how much?
Determine the duration of this node?
Yes or no - is the node on the critical path?