Question: he table below displays the EST-ECT LCT-LST information for a project. (The time is measured by a unit of day.) A A B C D

he table below displays the EST-ECT LCT-LST
he table below displays the EST-ECT LCT-LST information for a project. (The time is measured by a unit of day.) A A B C D E F G EST 05 5 10 10 15 19 ECT 5 10 8 19 15 18 21 LCT 5 5 10 11 19 16 19 21 LST 0 5 8 10 11 16 19 Please use the information in the table to decide which option is CORRECT. o If activity C is completed on day 10, the progress of the project will not be delayed. Activities with zero slack time form the critical path, that is ABDG The minimum amount of time it requires to complete the project is 21 days. All of the above