Question: The table below displays the EST-ECT LCT-LST information for a project. (The time is measured by a unit of day.) B C D E TI

The table below displays the EST-ECT LCT-LST
The table below displays the EST-ECT LCT-LST information for a project. (The time is measured by a unit of day.) B C D E TI G H EST 10 2 2 9 6 6 10 15 ECT 2 9 6 15 8 10 13 18 LCT 2 9 7 15 9 12 15 18 LST 0 2 3 9 7 8 12 15 Please use the information in the table to decide which option is WRONG. Activity E has a slack time of 1 day. The completion time of the project is 18 days If activity G starts on day 12, the progress of the project will not be affected. None of the above