Question: The table below displays the EST-ECT LCT-LST information for a project. (The time is measured by a unit of day.) A A B D E

The table below displays the EST-ECT LCT-LST
The table below displays the EST-ECT LCT-LST information for a project. (The time is measured by a unit of day.) A A B D E F G EST 0 3 3 8 10 15 18 ECT 3 8 10 15 15 18 20 LCT 3 10 10 18 15 18 20 LST d 5 3 11 10 15 18 Please use the information in the table to decide which option is WRONG. Activity D has a slack time of 3 days The completion time of the project is 20 days If activity D starts on day 10, the progress of the project will not be affected. Activities with zero stack time for the critical path, that is ABDG O None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!