Question: Here is a CPM network with activity times in weeks: A. Determine the critical path B. How many weeks will the project take to complete?

Here is a CPM network with activity times in weeks:

Here is a CPM network with activity times in

A. Determine the critical path

B. How many weeks will the project take to complete?

C. Suppose F could be shortened by 2 weeks and B by 1 week. By how many weeks would this reduce the project duration ?

(B(5) C(6) (A(7) G(3) (D(6) E(4) F(8)