Question: Here is a CPM network with activity times in weeks: B(5) C(6) (A(7) G(3) (D(6) E(4) F(8) a. Determine the critical path. O A-B-C-D O

Here is a CPM network with activity times in
Here is a CPM network with activity times in weeks: B(5) C(6) (A(7) G(3) (D(6) E(4) F(8) a. Determine the critical path. O A-B-C-D O A-E-F-D A-E-G-C-D b. How many weeks will the project take to complete? Number of weeks Prey 1 of 8 Next >