Question: Task Duration Predecessors A 4 B 6 C 7 A, B D 8 B E 5 B F 5 C G 7 D H 8

Task Duration Predecessors A 4 B 6 C 7 A, B D 8 B E 5 B F 5 C G 7 D H 8 D, E I 4 F, G, H

Draw the network and find Project Duration, Critical Path, and the ES, LS, EF, LF, and slack times for each task.