Question: Here is the information about the project: Activity Immediate Predecessors activity time A N/A 3 B A 2 C B 1 D C 1 E
-
Here is the information about the project:
Activity Immediate Predecessors activity time A N/A 3 B A 2 C B 1 D C 1 E G, C 2 F C, D 3 G B 5 H F 4 Make sure The Earliest Starting Time for Activity F is 7 before yo go on.
The Earliest Starting Time for Activity E is 6.
True
False
-
The Expected Total Project Completion Time is 14.
True
False
-
The Critical Path is A-B-C-D-F-H
True
False
-
If the activity E is delayed by 3 days, the new total project completion time will be 15 days.
True
False