Question: Here is the information about the project: Activity Immediate Predecessors activity time A N/A 3 B A 2 C B 1 D C 1 E

  1. Here is the information about the project:

    Activity Immediate Predecessors activity time
    A N/A 3
    B A 2
    C B 1
    D C 1
    E G, C 2
    F C, D 3
    G B 5
    H F 4

    Make sure The Earliest Starting Time for Activity F is 7 before yo go on.

    The Earliest Starting Time for Activity E is 6.

    True

    False

  1. The Expected Total Project Completion Time is 14.

    True

    False

  1. The Critical Path is A-B-C-D-F-H

    True

    False

  1. If the activity E is delayed by 3 days, the new total project completion time will be 15 days.

    True

    False