Question: I am not sure how to complete step 5 and 6. Could you please help me solve the last 2 steps? Identifier Activity Predecessor Duration
I am not sure how to complete step 5 and 6. Could you please help me solve the last 2 steps?
| Identifier | Activity | Predecessor | Duration | Cost | Crash Duration | Crash Cost |
| A | Create Blueprint | - | 5d | $300 | 5d | $300 |
| B | Buy Materials | A | 8d | $250 | 5d | $400 |
| C | Identify Lazy Dog Owners | A | 2d | $100 | 2d | $100 |
| D | Collect Poop | A | 6d | $300 | 3d | $600 |
| E | Make Catapult | B,C | 3d | $150 | 2d | $300 |
| F | Get Launch Approval | C,D | 4d | $275 | 3d | $300 |
| G | Launch Poop | E,F | 9d | $700 | 8d | $900 |
The city of Atlanta is fed up with lazy dog owners leaving their dogs droppings on sidewalks and in the road. They have commissioned the creation of a catapult to solve their problem. You are the project manager for the construction of the new device, named the CATAPOOP. Create an activity on node diagram to determine the base project duration and answer the following questions:
1. What is the baseline expected duration for this project?
2. What is the fastest the project can be completed? How much extra would it cost? (Basically, All Crash the schedule.
3. To crash the project one day, what activity would be crashed and how much would it cost?
4. To crash the project two days, what activities would be crashed and how much would it cost?
5. If the city offers a bonus of $125 per day for finishing early, what activities would be crashed, and how fast would the project be completed?
6. What sequential activities do you assess could be performed in parallel? What risks are associated with this?