Question: I don't need help with a. I don't understand how to get the numbers needed to compute the cycle time. 4) An assembly operation wishes

I don't need help with a. I don't understand how to get the numbers needed to compute the cycle time.
4) An assembly operation wishes to achieve an output of 240 units per eight-hour day. The task times and precedence information are contained the table below: Task Precedes (task) A B D E E F Duration (minutes) 0.2 0.4 0.2 0.4 1.2 1.2 1.0 |||| finish a) Create the precedence diagram b) Determine the minimum cycle time, the maximum cycle time, and the desired cycle timeStep by Step Solution