Question: identify the projects critical path below the network Diagram: a. Start-A-C-E-F-G-Finish b. Start-B-D-E-F-G-Finish c. Start-B-C-E-F-G-Finish d. Start-A-C-E-F-Finish Predecessors Activity A none B B none A
identify the projects critical path below the network Diagram:

| a. | Start-A-C-E-F-G-Finish
| |
| b. | Start-B-D-E-F-G-Finish
| |
| c. | Start-B-C-E-F-G-Finish
| |
| d. | Start-A-C-E-F-Finish
|
Predecessors Activity A none B B none A and B Activity Duration 1 Week 7 Weeks 5 Weeks 12 Weeks 10 Weeks 6 Weeks 3 Weeks D B E Cand D F E F G