Question: If A , B , and C are three activities connected with S S and F F ( combination ) relationships with 2 - day
If
A
B
and
C
are three activities connected with
S
S
and
F
F
combination
relationships with
day lag on each relationship. Their durations are
and
; respectively. What is the duration of the project: