Question: If A, B, and C are three activities connected with SS relationships only with 2day lag on each relationship. Their durations are 10, 5, and
If A, B, and C are three activities connected with SS relationships only with 2‐day lag on each relationship. Their durations are 10, 5, and 3, respectively. What is the duration of the project?