Question: If A, B, and C are three activities connected with FF relationships only with 2day lag on each relationship. Their durations are 5, 10, and
If A, B, and C are three activities connected with FF relationships only with 2‐day lag on each relationship. Their durations are 5, 10, and 3, respectively. What is the duration of the project?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts