Question: If A, B, and C are three activities connected with SS and FF (combination) relationships with 2day lag on each relationship. Their durations are 5,
If A, B, and C are three activities connected with SS and FF (combination) relationships with 2‐day lag on each relationship. Their durations are 5, 10, and 3, respectively. What is the duration of the project?