Question: If an activity whose normal duration is 12 days can be shortened to 10 days for an added cost of $1,500, the crash cost per
If an activity whose normal duration is 12 days can be shortened to 10 days for an added cost of $1,500, the crash cost per period is A. $1.500 O B. $500 OC. $13,000 OD.5750 OE. $15,000