Question: In a project network, the project completion time has been determined to be a random variable with a mean of 68 days and a standard

In a project network, the project completion time has been determined to be a random variable with a mean of 68 days and a standard deviation of 9 days (and can be assumed to be Normally distributed). How many days should we allow for this project to have approximately 90% probability of completion? (Provide one decimal place)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!