Question: In a project, Task 5 is showing 3 FS + 1 0 days under the Predecessors column. This means that: Group of answer choices Task
In a project, Task is showing FS days under the Predecessors column. This means that:
Group of answer choices
Task is the predecessor of Task with a lag of days
Task does not depend on Task at all
Task is the predecessor of Task with a lead of days
Task is the predecessor of Task with a lag of days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
