Question: In a project, Task 5 is showing 3 FS + 1 0 days under the Predecessors column. This means that: Group of answer choices Task

In a project, Task 5 is showing 3FS +10days under the Predecessors column. This means that:
Group of answer choices
Task 3 is the predecessor of Task 5, with a lag of 10 days
Task 5 does not depend on Task 3 at all
Task 3 is the predecessor of Task 5, with a lead of 10 days
Task 5 is the predecessor of Task 3, with a lag of 10 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!