Question: In a project, Task 5 is showing 3FS + 10days under the Predecessors column. This means that: OTask 5 is the predecessor of Task 3,

In a project, Task 5 is showing "3FS + 10days" under the Predecessors column. This means that: OTask 5 is the predecessor of Task 3, with a lag of 10 days Task 5 does not depend on Task 3 at all Task 3 is the predecessor of Task 5, with a lead of 10 days Task 3 is the predecessor of Task 5, with a lag of 10 days