Question: In a resource - constrained project, the first priority in assigning resources is usually given to activities with the: a . Smallest duration b .

In a resource-constrained project, the first priority in assigning resources is usually given to activities with the:
a. Smallest duration
b. Least slack
C. Most slack
d. Lowest identification number
 In a resource-constrained project, the first priority in assigning resources is