Question: In an MRP problem, Als an MPS Item.Every A requires 2 B's and 3 Cs. Every requires 5 Cs. All lead times are two periods.

In an MRP problem, Als an MPS Item.Every A
In an MRP problem, Als an MPS Item.Every A requires 2 B's and 3 Cs. Every requires 5 Cs. All lead times are two periods. All initial Inventory values are O. Use lot-for-lot method for order quantities for all items. If gross requirement for Ais 500 in period 8, what will be the planned order release for Bin period 4? Multiple Choice 500 o 1.500 1,000