Question: In making a backward pass through a network, activity L immediately precedes activities M, P, and T. The late start times for activities M, P,

In making a backward pass through a network, activity L immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 20, 17, and 15, respectively. What is the late finish time for activity L?