Question: In making a backward pass through a network, activity T immediately precedes three activities. What is the late finish time for activity T? Select one:

In making a backward pass through a network,
In making a backward pass through a network, activity T immediately precedes three activities. What is the late finish time for activity T? Select one: a. the activity time for activity T b. the largest LF for the three activities that activity T immediately precedes c. the smallest LS for the three activities that activity T immediately precedes d. the largest LS for the three activities that activity T immediately precedes e. the smallest LF for the three activities that activity T immediately precedes