Question: n making a backward pass through a network, activity L has an activity time of 6 and immediately precedes activities M, P, and T. The
n making a backward pass through a network, activity L has an activity time of 6 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 32, 27, and 26, respectively. The late finish times for activities M, P, and T are 39, 37, and 33, respectively. What is the late start time for activity L?
Group of answer choices
20
13
17
33
22