Question: In making a backward pass through a network, activity L has an activity time of 5 and immediately precedes activities M, P, and T. The
In making a backward pass through a network, activity L has an activity time of 5 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 22, 25, and 27, respectively. The late finish times for activities M, P, and T are 29, 31, and 33, respectively. What is the late start time for activity L?