Question: In making a backward pass through a network, activity L has an activity time of 4 and immediately precedes activities M, P, and T. The

In making a backward pass through a network, activity L has an activity time of 4 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 32, 27, and 26, respectively. The late finish times for activities M, P, and T are 39, 37, and 33, respectively. What is the late start time for activity L?

a. 22

b.17

c.13

d.33

e.30

1. What is the optimal solution to the following linear program?

Max 2X+4Y

Constraints: 2X+2Y 20 X+Y 10 X 0 Y 0

Group of answer choices

the program is infeasible

(20,0)

(0, 10)

the solution is unbounded

(10,0)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!