In making a backward pass through a network, activity Lhas an activity time of 4 and immediately precedes activities M, P and T The late start times for activities M, P, and Tare 22 17 and 27 respectively. The late finish times for activities M P and Tare 29, 27 and 33, respectively What is the late start time for activity L? O A 13 22