Question: In project schedule management, which process primarily involves checking and managing changes to the project schedule? a . estimating activity durations b . developing the
In project schedule management, which process primarily involves checking and managing changes to the project schedule?
a
estimating activity durations
b
developing the schedule
c
controlling the schedule
d
estimating activity resources
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock