Question: In the space provided below create the network diagram that shows the relationship (logic) of project activities shown below and then number each event. 1.
In the space provided below create the network diagram that shows the relationship (logic) of project activities shown below and then number each event.
1. In a given project activities "A, B and C are initial activities that may begin at the same time
2. -----"D" cannot begin until "A" is complete.
3. ----- "B" must be complete before E can begin.
4. ----- "F" cannot start until "C" is finished.
5. ----- "G" cannot begin until "B" is finished.
6. ----- "G" and "D" must be done before "H" can begin.
7. ----- "I" cannot begin until "B" is finished.
8. ----- "J" can begin only after "F" and "I" are complete.
9. ----- Once "E" is complete, "K" can begin.
10. ---- The project will be finished when "H" "J" and "K" are complete.