Question: In the table below the activities with their precedence sequence and expected time (in weeks) are listed for the construction project: Activity J K Time

In the table below the activities with their precedence sequence and expected time (in weeks) are listed for the construction project:

In the table below the activities with their

In the table below the activities with theirIn the table below the activities with their

Activity J K Time (weeks) 12 8 6 YJE Z O Nodes 1-2 1-3 2-3 2-4 3-4 4-5 3-5 3 M N 2 7 P 6 The correct precedence network diagram for the given project is shown in Figure 2 Figure 1 Figure 3 Figure 1 M . N 5 P 3 Figure 2 M N 5 K 3 Figure 3 M N 5 K 3