Question: Inputs to the Define Activities process are: Select one: a . Project schedule, resource estimates, progress reports, and change requests. b . Scope management plan,
Inputs to the Define Activities process are:
Select one:
a Project schedule, resource estimates, progress reports, and change requests.
b Scope management plan, project network diagram, constraints, and assumptions.
c Schedule management plan, work breakdown structure, project schedule, and network diagram.
d Schedule management plan, scope baseline, enterprise environmental factors, and organizational process assets.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock