Question: Instruction: a) compute for expected time for each activity and the expected path duration ACTIVITY IMMEDIATE PREDECESSORS TIME ESTIMATES (days) A 2 B 3 6

Instruction: a) compute for expected time for

Instruction: a) compute for expected time for each activity and the expected path duration ACTIVITY IMMEDIATE PREDECESSORS TIME ESTIMATES (days) A 2 B 3 6 D A,B,C,E 12 E A,B,C,D, 15 F D 6 G D 7 H E 9 E 4 J B,F,G,H,I 12 K G 18 00 L H 7 M J,KL 9 Z s N FM 10 O IM 8 K,L,M,N,O 14 Q P 6