Question: Problem 15-6 (Static) Consider the following information about a small project: Task Duration Estimates Immediate Predecessors A 2 days None B 5 days A C

Problem 15-6 (Static)

Consider the following information about a small project:

Task Duration Estimates Immediate Predecessors
A 2 days None
B 5 days A
C 1 day B
D 2 days A
E 3 days B & D
F 12 days E & C

Click here for the Excel Data File

Problem 15-6 (Static) Consider the following b-1. Identify the critical path.

  • A-D-E-F

  • A-B-C-F

  • A-B-E-F

b-2. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.)

Problem 15-6 (Static) Consider the following

c. Which of these activities should the project manager track most closely?

  • A-B-E-F

  • A-D-E-F

  • A-B-C-F

Problem 15.6 Task Duration Estimate (in Days) Immediate Predecessors None B A B and D E and C Earliest Start (ES) Earliest Completion (EC) Immediate Task Predecessors A None B A CB D E B,D F CE Task Latest Completion Latest Start (LS) Immediate Successors None Slack F. E DE CF B CE A BD

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!