Question: Problem 15-6 (Static) Consider the following information about a small project: Task Duration Estimates Immediate Predecessors A 2 days None B 5 days A C
Problem 15-6 (Static)
Consider the following information about a small project:
| Task | Duration Estimates | Immediate Predecessors | |
| A | 2 | days | None |
| B | 5 | days | A |
| C | 1 | day | B |
| D | 2 | days | A |
| E | 3 | days | B & D |
| F | 12 | days | E & C |
|
| |||
Click here for the Excel Data File
b-1. Identify the critical path.
-
A-D-E-F
-
A-B-C-F
-
A-B-E-F
b-2. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.)

c. Which of these activities should the project manager track most closely?
-
A-B-E-F
-
A-D-E-F
-
A-B-C-F
Problem 15.6 Task Duration Estimate (in Days) Immediate Predecessors None B A B and D E and C Earliest Start (ES) Earliest Completion (EC) Immediate Task Predecessors A None B A CB D E B,D F CE Task Latest Completion Latest Start (LS) Immediate Successors None Slack F. E DE CF B CE A BD