Question: Item 2 1 0 points Return to questionItem 2 Problem 5 - 8 ( Algo ) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR
Item
points
Return to questionItem
Problem Algo
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E Cmedia:cmpng D
F D
G F
H Emedia:cmpng G
What is the critical path?
multiple choice
ABEH
ACEFGH
ABDEH Correct
ACEH
How many weeks will it take to complete the project?
Which activities have slack, and how much?
multiple choice
Ecm weekssc Hcm week. Incorrect
Ccm weekssc Fcm weeksc Gcm week.
Bcm weekssc Dcm weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock