Question: JIT & Lean Production TBP 5 Demand Rate (D) = 60 units/hr Lead Time (T) = 40 hours Container Capacity (C) = 20 units Safety

JIT & Lean Production

TBP 5

Demand Rate (D) = 60 units/hr

Lead Time (T) = 40 hours

Container Capacity (C) = 20 units

Safety Factor (x) = 10%

Part a: How many kanban production cards are needed?

Part b: How many hours of demand will these cards represent?

Part c: Suppose the demand rate doubles but the lead time is cut in half. Will this make a difference in inventory level?