Question: Job Processing Time (days) Job due date (days) A 4 7 B 7 4 C 8 11 D 3 5 E 5 8 Using the
| Job | Processing Time (days) | Job due date (days) |
| A | 4 | 7 |
| B | 7 | 4 |
| C | 8 | 11 |
| D | 3 | 5 |
| E | 5 | 8 |
- Using the shortest processing time rule, in which order should the jobs be processed? (4 points)
- Using the earliest due date dispatching rule, in which order should the jobs be processed? (4 points)
- What is the average flow time by using shortest processing time dispatching rule? (6 points)
- What is the average number of jobs by using shortest processing time dispatching rule? (6 points)
- What is the average lateness by using shortest processing time dispatching rule? (6 points)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts