Question: Later activity Previous Activity Weekly Time A - 10 B - 5 C A 5 D AB 10 E B 14 F C,D 14 G

Later activity

Previous Activity

Weekly Time

A

-

10

B

-

5

C

A

5

D

AB

10

E

B

14

F

C,D

14

G

E

6

H

F,G

4

I

G

7

J

i

8

The Required:

1- work network drawing

2- Calculate the early start, early end, late start and late end

3- Finding the critical path