Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. Theactivities, immediate predecessors, and times appear in the accompanyingtable:
| Activity | Immediate Predecessor(s) | Time (days) |
| A | 2 | |
| B | 5 | |
| C | 1 | |
| D | B | 10 |
| E | A, D | 3 |
| F | C | 6 |
| G | E, F | 8 |
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are
c) The project length for the leadership training program development project= ___ days.
d) Slack time for each of the activities is:
| Activity | Slack Time |
| A | enter your response here |
| B | enter your response here |
| C | enter your response here |
| D | enter your response here |
| E | enter your response here |
| F | enter your response here |
| G | enter your response here |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock