Question: Loans are evaluated in a process with two resources. The first resource has a capacity of 30 loans per hour. The capacity of the second
Loans are evaluated in a process with two resources. The first resource has a capacity of 30 loans per hour. The capacity of the second resource is 38 loans per hour. Demand for this process is 40 loans per hour. Instruction: Round your answer to three decimal places. What is the cycle time of this process (in minutes)? minutes