Question: Microsoft Project Essential Training 6. When you want to delay tasks, you add _____ duration values in the _____ field. Select an answer: elapsed; Delay

Microsoft Project Essential Training

6. When you want to delay tasks, you add _____ duration values in the _____ field.

Select an answer:

elapsed; Delay

elapsed; Leveling Delay

regular; Delay

regular; Leveling Delay

7. A resource is overallocated by two simultaneous assignments. One of the tasks is very short, while the other task is long. Which technique provides an easy solution to this situation?

Select an answer:

assigning a resource with available time to the short task

assigning multiple resources to both tasks

delaying the long task to finish after the short one is complete

splitting the long task

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!